+ NASA
Home > EVM > Tutorial > NASA
EVM Tutorial
NASA EVM Tutorial (Concluded)

Schedule variance chart
In
our example the task was planned to have accomplished $100k worth of
work in twelve months, but the real accomplishment was only $60k. The
graph shows a "behind schedule" condition. The schedule variance in
dollars would be a negative $40k, the difference between the earned
value accomplished ($60k), and the value of the planned work ($100k)
to date. According to our formula then:
$60k - $100k = ($40k)
The value earned for
the work performed compared with the actual cost incurred for
the work performed (taken directly from the contractor's accounting
systems), provides an objective measure of cost efficiency. Any difference
is called a cost variance.
Earned
Value - Actual Costs = Cost Variance (CV)
A negative variance
means more money was spent for the work accomplished than was planned.
Conversely, a positive variance means less money was spent for the
work accomplished than was planned to be spent.
Cost variance chart
From
the performing organization's own accounting system, we determine the
actual costs for performing the $60K work was $110K.
When the actual costs
are compared with the earned value of $60k, the difference is the cost
variance. The earned value of $60k less the actual cost of $110k, is
a negative cost variance of $50k. In this example, the task is in an
overrun condition by $50k.
$60k
- $110k = ($50k)
Analysis of these
variances should reveal the factors causing the deviation from plan.
The Task Manager
uses this information in conjunction with his knowledge of the task,
to project an estimate to complete for this task. The Task Managers
analyzes variances resulting from comparisons of these five basic data
elements; planned work, work accomplished, actual costs, total budget
at completion and the estimate at completion. The work breakdown structure
provides a useful framework for summarizing this performance information
for all levels of management.
Earned value improves
on the "normally used" spend plan concept (budget versus
actual incurred cost) by requiring the work in process to be quantified.
The planned value, earned value, and actual cost data provides an objective, quantifiable measurement
of performance, enabling trend analysis and evaluation of any cost
estimate at completion within multiple levels of the project.
EVM is a valuable
tool in the Project Manager's "toolbox" for gaining valuable insight
into project performance and is the tool that integrates technical,
cost, schedule and risk management. In addition, EVM provides valuable
quantifiable performance metrics for forecasting at-completion cost
and schedule for their project.
Back
|