Script has no functionality
Skip navigational links    
  NASA - National Aeronautics and Space Administration
 
About NASA Latest News Multimedia Missions My NASA Work for NASA
spacer
Earned Value Management (EVM) Overview Tutorial Requlations and Requirements EVM Focal Point Council Implementation Handbooks EVM Training Information EVM Reports Links to Other EVM Sites EVM Glossary EVM Acronyms  

+ NASA Home > EVM > Tutorial > NASA EVM Tutorial

NASA EVM Tutorial (Concluded)

Schedule variance chart
Schedule variance chart

In our example the task was planned to have accomplished $100k worth of work in twelve months, but the real accomplishment was only $60k. The graph shows a "behind schedule" condition. The schedule variance in dollars would be a negative $40k, the difference between the earned value accomplished ($60k), and the value of the planned work ($100k) to date. According to our formula then:

$60k - $100k = ($40k)

The value earned for the work performed compared with the actual cost incurred for the work performed (taken directly from the contractor's accounting systems), provides an objective measure of cost efficiency. Any difference is called a cost variance.

Earned Value - Actual Costs = Cost Variance (CV)

A negative variance means more money was spent for the work accomplished than was planned. Conversely, a positive variance means less money was spent for the work accomplished than was planned to be spent.

Cost variance chart
Cost variance chart

From the performing organization's own accounting system, we determine the actual costs for performing the $60K work was $110K.

When the actual costs are compared with the earned value of $60k, the difference is the cost variance. The earned value of $60k less the actual cost of $110k, is a negative cost variance of $50k. In this example, the task is in an overrun condition by $50k.

$60k - $110k = ($50k)

Analysis of these variances should reveal the factors causing the deviation from plan.

The Task Manager uses this information in conjunction with his knowledge of the task, to project an estimate to complete for this task. The Task Managers analyzes variances resulting from comparisons of these five basic data elements; planned work, work accomplished, actual costs, total budget at completion and the estimate at completion. The work breakdown structure provides a useful framework for summarizing this performance information for all levels of management.

Earned value improves on the "normally used" spend plan concept (budget versus actual incurred cost) by requiring the work in process to be quantified. The planned value, earned value, and actual cost data provides an objective, quantifiable measurement of performance, enabling trend analysis and evaluation of any cost estimate at completion within multiple levels of the project.

EVM is a valuable tool in the Project Manager's "toolbox" for gaining valuable insight into project performance and is the tool that integrates technical, cost, schedule and risk management. In addition, EVM provides valuable quantifiable performance metrics for forecasting at-completion cost and schedule for their project.

Back

  USAGov - Government Made Easy

ExpectMore.gov
+ Freedom of Information Act
+ Budgets, Strategic Plans and Accountability Reports spacer
+ The President's Management Agenda
+ NASA Privacy Statement, Disclaimer,
spacerand Accessibility Certification

+ Inspector General Hotline
+ Equal Employment Opportunity Data Posted
spacerPursuant to the No Fear Act

+ Information-Dissemination Priorities and
spacerInventories
+ NASA Safety Reporting System
NASA

Curator: MITS
NASA Official: Jerald Kerby
Last Updated: January 22, 2010
+ Contact NASA
+ SiteMap
   
     

NASA Home